Stoughton residents,
Thank you for your patience as we continue to improve our infrastructure. We plan to pave an additional 27 streets this construction season. The duration of each completed street is roughly three weeks. A normal course of events is stated below:
1.) Roadway Dig Safe completed
2.) Contractor mobilization and cut driveways to match future final paving
3.) Milling of existing roadway
4.) Pave leveling course of pavement to prepare for final course
5.) Ensure all surface gas, water or drainage structures set to appropriate grade
6.) Final paving
7.) Pave driveway edges to meet new roadway elevation
8.) Striping (if necessary)
9.) Loam/seed and/or backfill any elevation changes on roadway edges
2025 Planned paving projects listed here:
| CARYL ROAD |
| CHARLES CIRCLE |
| COLUMBUS AVENUE |
| COMMONWEALTH AVENUE |
| COURTNEY AVENUE |
| DEADY AVENUE |
| DEXTER STREET |
| DONALD ROAD |
| EWING DRIVE |
| FAY AVENUE |
| GOLDEN ROAD |
| GREENWOOD AVENUE |
| HALLIDEN PLACE |
| HALLIDEN STREET |
| HEELAN AVENUE |
| HOLMES AVENUE |
| LEACH STREET (EAST OF PROSPECT ONLY) |
| LILLIAN ROAD |
| LOWE AVENUE EXTENTION |
| MEADOWBROOK LANE |
| MERRILL STREET |
| ROBICHAU CIRCLE |
| RONALD WAY |
| RUTH ROAD |
| TROWBRIDGE CIRCLE |
| WALNUT COURT |
WHITNEY AVENUE
|