Thank you for your patience as we continue to improve our infrastructure. We plan to pave an additional 27 streets this construction season. The duration of each completed street is roughly three weeks. A normal course of events is stated below:

1.) Roadway Dig Safe completed 
2.) Contractor mobilization and begin milling of existing roadway
3.) Level course of pavement to prepare for final course
4.) All surface gas, water or drainage structures set to appropriate grade
5.) Final paving 
6.) Striping (if necessary)
7.) Loam/seed and/or backfill any elevation changes on roadway edges

2025 Planned paving projects listed here:
CARYL ROAD
CHARLES CIRCLE
COLUMBUS AVENUE
COMMONWEALTH AVENUE
COURTNEY AVENUE
DEADY AVENUE
DEXTER STREET
DONALD ROAD
EWING DRIVE
FAY AVENUE
GOLDEN ROAD
GREENWOOD AVENUE
HALLIDEN PLACE
HALLIDEN STREET
HEELAN AVENUE
HOLMES AVENUE
LEACH STREET (EAST OF PROSPECT ONLY)
LILLIAN ROAD
LOWE AVENUE EXTENTION
MEADOWBROOK LANE
MERRILL STREET
ROBICHAU CIRCLE
RONALD WAY
RUTH ROAD
TROWBRIDGE CIRCLE
WALNUT COURT
WHITNEY AVENUE

Facebook Twitter Email

Other News in Home

Feb 2026 Cedar Hill Stoughton-2

Boston Children's Hospital Blood Drive

Posted on: January 16, 2026 | Last Modified on: January 16, 2026
2025 Dog License

It's Time to Renew Your Dog's License!

Posted on: January 15, 2026

Snow Related Information for Residents

Posted on: December 24, 2025
Aerial

Website Personalization Now Available!

Posted on: November 22, 2016
home-office-working-on-a-laptop-picjumbo-com

Create an Account

Posted on: November 22, 2016
News Placeholder

Stay connected!

Posted on: November 22, 2016
Building

Keep in Touch

Posted on: November 22, 2016
Aerial

Website Personalization Now Available!

Posted on: November 22, 2016